91青草久久久久久清纯_最新中文字幕av专区_皇上破了宫女的处h_周于希裸全身任何部位无遮挡

EN
The flue gas cleaning (FGC) project contracted by Huaxing-east for the waste incineration power plant in Qianzishan circular economy industrial park, Wuhan Hubei, passed 72+24 hours trial operation.
2023.02.23
The FGC project undertaken by HXET for waste-to-energy plant in Qianzishan circular economy industrial park, Wuhan Hubei,  passed 72+24 hours of trial operation on December 9, 2022.
The treatment capacity of the plant is 1500 t/d. A set of 2x750 t/d waste incinerator, 1x35 MW condensing steam turbine, 1x40 MW generator, and supporting facilities will be constructed. The FGC adopts the process of "SNCR (not within the scope of contractor) + semi-dry with Ca(OH)2 + dry method with sodium bicarbonate + activated carbon injection + bag filter + low-temperature SCR + catalyst from Mitsubishi Heavy Industries". It is an equipment supply project of Huaxing.
The achievements of HXET in Hubei Province include Wuhan Xingou, Wuhan Qianzishan, Shishou, Dangyang, Lichuan, Shiyan, Suizhou, Huanggang Luotian, Xianning, Jingzhou Public Security, Jingzhou Jianli, Xiaogan, Huanggang Hong'an, Jingzhou Honghu, Xiantao, Jingmen Shayang, etc.
For more information, please click or scan below!

Follow us!