The flue gas cleaning system of the waste incineration power generation in Gengma, Lincang, Yunnan Province, constructed by HEPT, has passed the 72-hour + 24-hour trial operation
2024.07.31
The flue gas cleaning project of Gengma Municipal Solid Waste Incineration Power Generation Project in Lincang, Yunnan Province, undertaken by our company, passed a 72+24-hour trial operation on July 5, 2024.
The total design scale of the project is 300 tons of domestic waste per day, and the supporting construction of 1x300t/d mechanical grate waste incineration boiler +1xN6MW steam turbine generator set.The FGC adopts the treatment process of "SNCR denitration + semi-dry deacidification + dry deacidification + activated carbon injection + bag filter + fly ash conveying, storage, and stabilization ". It is an EP project of Huaxing.
Huaxing East Co.'s performance in Yunnan Province includes multiple projects such as Qujing, Yuxi Jiangchuan Tonghai Huaning, Lincang Gengma, Honghe Hani and Yi Autonomous Prefecture, Honghe Hani and Yi Autonomous Prefecture Jianshui, Kunming Songming, Kunming Xishan, Kunming Wuhua, Xishuangbanna Dai Autonomous Prefecture Jinghong, Wenshan Zhuang and Miao Autonomous Prefecture Yanshan, Wenshan Zhuang and Miao Autonomous Prefecture Xichou, Lijiang, etc.